Fulfilment Process
| The fulfilment process of guarantee obligations differs by the type of guarantee. As for the guarantee for housing completion, the process is divided into performance of project completion and refund of housing payments. |
| The fulfilment of guarantee for defect repairs is initiated upon receipt of a claim for fulfilment, and guarantee obligations are determined through defect investigation and agreement with residents. |
What Is Defect Repairs Guarantee Incident?
When a defect that falls under the category of facilities subject to defect repair specified in Enforcement Decree of the Housing Act occurs within the statutory defect liability period by construction type, and a principal debtor fails to perform its obligations without justifiable causes despite guarantee creditors’ request for repairing, it constitutes the defect repairs guarantee incident.
Fulfilment Process of Defect Repairs Guarantee
-
Fulfilment Process of Defect Repairs Guarantee : Claim for Fulfilment of Defect Repairs Claim for Fulfilment of Defect Repairs - A group representing homeowners makes a claim for defect repairs to a principal debtor. In case where the principal debtor fails to respond to the claim, the homeowners association files a claim for fulfilment of guaranteed obligations by submitting required documents such as Defect Repairs Fulfilment Claim, etc. to HUG.
-
Fulfilment Process of Defect Repairs Guarantee : Field Investigation Field Investigation - HUG verifies the claim and submitted documents and gives notice to the applicable housing about an upcoming field investigation. Then, HUG conducts defect investigation into affected units by visiting them and into affected common areas.
-
Fulfilment Process of Defect Repairs Guarantee : Determination of Guaranteed Obligations by Defect Type Determination of Guaranteed Obligations by Defect Type - HUG determines if the defects verified through the investigation fall under its guaranteed obligations pursuant to the Enforcement Decree of the Housing Act.
-
Fulfilment Process of Defect Repairs Guarantee : Agreement with Homeowners Association on Repair Items Agreement with Homeowners Association on Repair Items - HUG reaches an agreement with homeowners association on defect items that fall under guaranteed obligations through consultation.
-
Fulfilment Process of Defect Repairs Guarantee : Payment to Homeowners Association Payment to Homeowners Association - HUG calculates the actual costs of defect repair construction in accordance of bylaws and pays the amount to the homeowners association in cash.
Non-guaranteed Liabilities
HUG has no guaranteed obligations to fulfil any of the following liabilities: (applicable to all guarantee certificates issued since Dec. 05, 2012)
- 1. Defects occurred due to natural disaster, war, civil war, or other similar causes
- 2. Defects occurred due to guarantee creditor’s delinquency of fiduciary duty in terms of maintenance, repair, and management of apartment common areas
- 3. Defects occurred due to violation of duties under related laws, management rules, and maintenance contract
- 4. Any area constructed differently from design drawing or not-constructed, defects in design, construction in violation of housing construction regulations, allowable error pursuant to Building Act, defects recognized in temporary move-in approval and other defects occurred before move-in inspection
- 5. Defects that fall under the category of facilities subject to defect repair specified in Enforcement Decree of the Housing Act occurred after the statutory defect liability period by construction type
- 6. Defects occurred due to changes in structure or functions made by residents or users
- 7. Defects that do not affect usability, safety, or structure of housing
- 8. Defects caused by the use of poor building materials in violation of related laws and regulations or illegal and unreasonable supervision/ move-in inspection and such cause is easily distinguishable
- 9. Defects caused by the damage, theft, loss, etc. of components and machinery attached to apartment buildings
- 10. Defects generally caused by natural wear-out including weathering, rust, mold, freeze and burst, contamination of underground water, drought, discoloration, withering of garden trees, etc.
- 11. Defects caused by fire or the third party (including defects caused by other construction near the apartment building, or one by gas explosion)
- 12. Cost of defect repairs arbitrarily conducted by guarantee creditors without consent from HUG
- 13. Physical and property damage other than the defects in apartment buildings
- 14. Defects caused in the process of moving-in and moving-out, and other defects for which a guarantee creditor is responsible including those occurred in “minus-option” part of house where homebuyer got a discount from house price under the condition that homebuyer will conduct finishing work, etc.